25 March 2010

SS resigned...

Got call from CSA that the SS has resigned due to some personal reason. He is quite good guy and did a good job on the house. I wish he would have stayed till the end. Met him today at the site by accidentally, he was handing over the job to the new SS. Wished all the best and good luck.

As the handover department is quite busy, may be the new SS can do the handover. Most probably looks like another 5 - 6 weeks.

Was just passing by the house, was not carrying the camera took some photos with the Mobile phone.


Kitchen is almost completed - except the free standing and range hood.
The splash back and benchtop are blending well.

Bathroom tiling and fit off almost completed

Now to the sensational Ensuite - may be this was one of the reasons we choose Regatta 288.
Very happy with selection, it turned out really well.

Mirror missing yet,

May be we can fit the whole family here.. :-)

Choose the bamboo floor, it is more harder and 14mm of real hard pressed bamboo and environmentally friendly. Put down the deposit for it, will most probably will be laying the floor ourself with the help of brother and a friend. Will save atleast $1500 with DIY solution.

Bayside - Wife wants this lighter color.

I like this - gives more like real timber look
Will be deciding on the color this weekend. More real pics can be found on this website http://crikeybamboo.com.au/gallery.html.

09 March 2010

Long time no Update..

Hello All,

Dear blog followers/readers accept my sincere apologies for not posting any updates from a long time. As I have been away and bit of tragedy happen back home in India. It took time to recover from that. Was busy with work and other things, was always thinking of posting but couldn't do it. Staying away from wife also make things hard,she is staying back home. So anyhow, by the time I came back 3rd week of Jan - plaster was on. Had plans to pre-plaster inspection, unfortunately that didn't happen. SS seems to be good and always assures everything will be fixed and will get good house,just hoping every thing is fine.

Current status is the house is in practically completion stage. Had few issues with wet areas, frame, slab, bricks motor, slab hole and etc...seems to be/will fixed.

Here are some current images...please feel free to comment and let me know if you guys need to see any more old pictures....Thanks!


From Ensuite/Master bedroom


Theater/Family room door - its been stained, seem to be they will do layer before hand over


From theater room

Kitchen view from family

Meals area

Kitchen splash back and benchtop

Kitchen

Door handle

Entry point

Our lovely front door(upgrade)

Porch and entry doorSelected carpet sample

Garage door - seems to be looking ok - not sure the colour above it..



We are quite happy with the selections

This is long story of them not doing the waterproofing properly. It seems be a lump on the board. Is this acceptable?

16 December 2009

Wrapped

Got some more pics from another friend(Thanks Imran).
House is now wrapped. It seems to be roof tiles are not yet completed.
Bricks are delivered now and I think the bricks might have started by now. Can't wait to see how they will look like.





I think brikie is organising bricks

Nice silver foil inside and green outside


Is something wrong with this, there is a gap or not nailed properly.

Hope the bricks will be completed before Christmas slow down period. Base and Frame invoices received and sent to the Bank. Hope will get the FHBG will be processed soon. RBA has increased the rate again, wondering when they will stop rising the rate.

07 December 2009

Plubming rough and Roof tiles...

My friend(Thanks Anand) has sent some house pics.
Looks like plumbing rough has been completed. Roof tiles seems to be completed.
Wondering where the bricks are??
Quite happy with the progress.



Roof looks quite big


Quite happy to see the roof tiles color is blended well with fascia/gutter.

03 December 2009

Timber Frame, Fascia and Gutter are done..

Received photos from a helpful blog Friend(nice work Fruitty, thanks), looks like its really progressing well.
Also got update from CA about the progress till now and Plumbing and Roof is scheduled for next week.
So if things go well will be all wrapped up before Christmas.
Relaxed a bit now!

Some pics.
Front view..Wondering if Timber post needs to be in the concrete.


Side view

Corner View
Right side view

Front temp door

Upgraded timber windows to the façade

Meals area

Roof...Looks good

Double Garage

Left side view..we wanted more space on this side as living and meals are on this side, unfortuantely(long story..) ended up on having 2.7 M on North side of the house.

Thanks for sending the pictures in, when I am still away Fruitty.

27 November 2009

In India..

Reached India(Hyderabad - click if interested to know know more about my home town) on 27th, will be here till Jan 1st. Taking care of Mom, she got diagnosed with Gall Balder cancer...

Received 1st Invoice today by E-mail for the Slab, they also sent the Inspection report. Looks ok, all it says is H has built the slab according to specifications, plans and BCA.

I hope things will progress well in my absence...
Will try to post some pics soon..

Will keep on posting about the previous things, so dates will be out of sequence.

24 November 2009

Search for Dream Home

Started to look around display homes to get an idea of what we need.Selected one home from each of the big builders like Porter Davis, Metricon and Henley.Discussed with sales guys about our choice but Alas!! every one told us that our block is meant for two storey homes.We very depressed as we needed just a single storey home, moreover two storey home was not very affordable.Luckily the sales consultant of Henley told we can fit Regatta 288 now Regatta Q1 on our land provided we chose a smaller porch. We were very happy as we really loved that home.
Finally we are building Regatta 288 with many surprises coming ahead, which we were not aware of at that time.
Here is the link of Original home plan:
http://www.vic.henley.com.au/#/House/clendonvale/25/FloorPlans/25/